The calculation of constraints at the Gorontalo 2x25 MW Orchid PLTU plant obtained a LOLP value of 37.84 days per year. This value is still above the reliability value of PLN standards. This is because in Unit 2, there were POs (Planned Outages) and MOs (Maintenance Outages) in June-July 2021, which were in the form of a first-year inspection in July. The FOR (Force Outage Rate) value is calculated based on disturbance data from plants in 2021. So a scenario was carried out for reliability improvements in the plant. From scenario 1, a reliability value of 36.86 was obtained, and scenario 2 obtained 16.16 days per year; scenario 3 had a value of 1.54 days per year.

Downloads

Download data is not yet available.

References

A. N. Widiastuti, Sarjiya, K. A. Pinandhito and E. T. Prastyo, "Evaluasi Keandalan Perencanaan Pembangkit Wilayah Jawa Bali dengan Mempertimbangkan Ketidakpastian Peramalan Beban," JNTETI, vol. VOl 6; No 2, pp. 230-234, Mei 2017.

A. J. Wood, B. F. Wollenberg and G. B. Sheblé, Power Generation Operation and Control, 3rd Edition, New Jersey: John Wiley and Sons, 2013.

I. T. Yuniahastuti, I. Sunaryantiningsih and B. Olanda, "Contactless Thermometer sebagai Upaya Siaga Covid-19 di Universitas PGRI Madiun," Jurnal ELECTRA : Electrical Engineering Articles, pp. 28-34, 2020.

A. Setiawan, A. Zainal, S. Budi, and G. Iwa. "Electricity Tariff Simulation on The Largest Electric Power System in Indonesia Using The Time Of Use and Critical Peak Pricing Schemes Based on Revenue Neutrality." In 2021 IEEE 4th International Conference on Power and Energy Applications (ICPEA), pp. 93-98. IEEE, 2021.

I. A. I. R. Irna Tri Yuniahastuti, "Load frequency control (LFC) of micro-hydro power plant with Capacitive Energy Storage (CES) using Bat Algorithm (BA)," in International Seminar on Application for Technology of Information and Communication (ISemantic), pp. 147-151. Semarang, 2016.

R. A. Putra and I. T. Yuniahastuti, "Perhitungan Keandalan Pembangkit Loss of Load Probability (LOLP) untuk N unit Pembangkit," Jurnal ELECTRA: Electrical Engineering Articles, vol.1, pp. 13-19, 2021.

R. D. Laksono, I. T. Yuniahastuti and A. P. P. Prakoso, "Skenario Peningkatan Keandalan Sistem Pembangkit Tenaga Listrik Di Wilayah Bali Berdasarkan LOLP," Jurnal ELECTRA : Electrical Engineering Articles, vol. 2, no. 1, pp. 39-45, 2021.

R. A. Putra, I. T. Yuniahastuti and R. D. Laksono, "Skenario Perbaikan Nilai Keandalan Loss of Load Probability pada PLTH Pantai Baru Pandansimo," Jurnal ELECTRA : Electrical Engineering Articles, vol. 2, no. 1, pp. 16-22, 2021.

A. Zaki, I. T. Yuniahastuti and I. Sunaryantiningsih, "Perhitungan Keandalan Sistem Distribusi 20 KV Menggunakan Metode SAIDI Dan SAIFI Di PT. PLN (Persero) ULP Maospati," Jurnal ELECTRA : Electrical Engineering Articles, vol. 2, no. 2, pp. 23-28, 2022.

K.R. Khan, A. A. Abou-Arkoub and M.J. Newtown. "Evaluation of Loss of Load Probability and Expected Energy Generatioan in Multi-Area Interconnected System with Wind Generating Units", New York: State Universitu of New York, IEEE International Conference on Smart Energy Grid Engineering (SEGE), pp. 1-8. IEEE, 2013.

D. Marsudi, Operasi Sistem Tenaga Listrik, Yogyakarta: Graha Ilmu, 2006.

"Bidang Perencanaan Sistem, Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2015-2024," PT PLN Persero, 2017.

R. R. Dharmawan and U. T. Kartini, "Analisis Indeks Keandalan PLTGU Blok 1 PT PJB UP Gresik Menggunakan Perhitungan Teorema Bayes dan Decomposisi LU," Jurnal Teknik Elektro, vol. 09 Nomer 03, pp. 658-666, 2020.

H. D. Laksono, "Aplikasi Logika Fuzzy pada Perkiraan Kebutuhan Energi Lisrik Jangka Panjang di Provinsi Sumatra Barat sampai tahun 2018," Jurnal Teknologi Informasi & Pendidikan, vol. Vol 3; No 1, pp. 42-53, Maret 2011.

"Badan Pusat Statistik," [Online]. Available: https://gorontalokota.bps.go.id/indicator/7/197/1/jumlah-pelanggan-listrik-pt-pln-persero-menurut-bulan-.html. [Accessed Agustus 2021].

I. Qamber, "Loss of Load Probability Effect in Four Power Stations," in International COnference on Fourth Industrial Revolution, University of Bahrain, 2019.

A, " PT PJB Service Unit PLTU Anggrek," Gorontalo, 2021.

R. F. S. Budi, M. D. Birmano and I. Bastori, "Pemodelan Perhitungan Indeks Lost of Load Probability untuk N Unit Pembangkit pada Sistem Kelistrikan Opsi Nuklir," Jurnal Pengembangan Energi Nuklir, vol. Vol 19; No 2, pp. 61-68, 2018.

Published

2023-11-30

How to Cite

[1]
I. T. Yuniahastuti and Y. Adi Kusuma, “Skenario Perbaikan Keandalan Pembangkit dengan Peramalan Beban Pada PLTU Anggrek Gorontalo”, GIJTSI, vol. 4, no. 02, pp. 88–98, Nov. 2023.