CRITICAL PATH ANALYSIS OF BOGOR UTILITY HUB E-COMMERCE ROOF DEVELOPMENT PROJECT SCHEDULING USING CPM AND PERT METHODS

Authors

  • Moch Agung Fahrezi Moch Agung Fahrezi
  • Kusmanto Kusmanto Program Studi Teknik Industri, Fakultas Teknik, Universitas Singaperbangsa Karawang
  • Sutrisno Sutrisno Program Studi Teknik Mesin, Fakultas Teknik, Universitas Singaperbangsa Karawang

DOI:

https://doi.org/10.35261/barometer.v8i2.8275

Abstract

This study discusses the project completion time in the construction of a utility located in the Bogor E-Commerce Hub warehouse using the CPM and PERT methods. In addition, the critical path in the sequence of project activities will also be identified using a Network Diagram. At the end of the discussion of this study, the probability or probability of completing this project is calculated and how big is the probability or possibility if this project is accelerated or slowed down. There are 13 sequences of activities in this project with a total time of 105 days and the activities that require the longest time are finishing activities which take 29 days and the shortest activity is 1 day. From the critical path analysis using the Network Diagram, it was found that all activities in this project are critical activities that cannot be postponed and must be carried out immediately after the previous activity has been completed. In the calculation using the CPM method, the results of the project completion are 105 days, while for the PERT calculation the results are 104.5 days. The probability of this project's completion time being accelerated to 104 days is 40.90%.

Downloads

Download data is not yet available.

References

N. Sembiring, Buku Ajar Manajemen Proyek Sebagai Panduan, 1st ed. Medan: Universitas Sumatera Utara, 2020.

Ashari, “Buku 1 Bahan Ajar Manajemen Proyek,” Bandung, 2011. [Online]. Available: https://digilib.polban.ac.id/files/disk1/84/jbptppolban-gdl-ashari-4157-1-manajeme-k.pdf.

E. Rita, N. Carlo, and Nandi, “Penyebab Dan Dampak Keterlambatan Pekerjaan Jalan Di Sumatera Barat Indonesia,” J. Rekayasa, vol. 11, no. 1, pp. 27–37, 2022, doi: 10.37037/jrftsp.v11i1.94.

A. Hakiim, W. Suhendar, and D. Agustina Sari, “Analisis Beban Kerja Fisik Dan Mental Menggunakan CVL Dan Nasa-TLX Pada Divisi Produksi PT X,” Barometer, vol. 3, no. 2, pp. 142–146, 2018, doi: 10.35261/barometer.v3i2.1396.

I. Soeharto, MANAJEMEN PROYEK (Dari Konseptual Sampai Operasional), 2nd ed. Jakarta: Erlangga, 1999.

M. Mazlum and A. F. Güneri, “CPM, PERT and Project Management with Fuzzy Logic Technique and Implementation on a Business,” Procedia - Soc. Behav. Sci., vol. 210, pp. 348–357, 2015, doi: 10.1016/j.sbspro.2015.11.378.

N. Susanto, R. Purwaningsih, and E. A. Abstrak, “Analisis Jaringan Kerja Dan Penentuan Jalur Kritis Dengan Critical Path Methode-Cpm (Studi Kasus Pembangunan Rumah Graha Taman Pelangi Type Milano Pada Pt Karyadeka Alam Lestari Semarang),” J@ti Undip J. Tek. Ind., vol. 1, no. 1, pp. 74–84, 2006, [Online]. Available: https://ejournal.undip.ac.id/index.php/jgti/article/view/2202.

A. T. Caesaron Dino, “Analisa Penjadwalan Waktu dengan Metode Jalur Kritis dan PERT pada Proyek Pembangunan Ruko (Jl. Pasar Lama No.20, Glodok),” JIEMS J. Ind. Eng. Manag. Syst., vol. 8, no. 2, pp. 59–82, 2015.

R. Amalia, M. A. Rohman, and C. B. Nurcahyo, “Analisa Penyebab Keterlambatan Proyek Pembangunan Sidoarjo Town Square Menggunakan Metode Fault Tree Analysis ( FTA ),” J. Tek. ITS, vol. 1, no. 1, pp. D20–D23, 2012.

J. Awuy, J. Tjakra, and P. A. K. Pratasis, “Metode Pelaksanaan Konstruksi Pekerjaan Atap Dan Plafon,” J. Tekno Unsrat, vol. 21, no. 84, pp. 707–712, 2023.

I. Agustiar and R. Handrianto, “Evaluasi Penjadwalan Proyek Menggunakan Metode CPM dan Kurva S (Studi Kasus : Pembangunan Gedung Perpustakaan SMK N 1 ‘XX’, Gresik),” Wahana Tek., vol. 07, no. 02, pp. 99–105, 2018, [Online]. Available: http://journal.unigres.ac.id/index.php/WahanaTeknik/article/view/788.

S. Badri, Dasar-Dasar Network Planning (Dasar - Dasar Perencanaan Jaringan Kerja). Yogyakarta, 1998.

Downloads

Published

2023-08-01

How to Cite

Fahrezi, M. A., Kusmanto, K., & Sutrisno, S. (2023). CRITICAL PATH ANALYSIS OF BOGOR UTILITY HUB E-COMMERCE ROOF DEVELOPMENT PROJECT SCHEDULING USING CPM AND PERT METHODS. Barometer, 8(2), 95–102. https://doi.org/10.35261/barometer.v8i2.8275

Issue

Section

Artikel